The Arizona Revised Statutes have been updated to include the revised sections from the 56th Legislature, 1st Regular Session. Please note that the next update of this compilation will not take place until after the conclusion of the 56th Legislature, 2nd Regular Session, which convenes in January 2024.
DISCLAIMER
This online version of the Arizona Revised Statutes is primarily maintained for legislative drafting purposes and reflects the version of law that is effective on January 1st of the year following the most recent legislative session. The official version of the Arizona Revised Statutes is published by Thomson Reuters.
33-984 - Lien for labor or materials furnished mill, factory or hoisting works
33-984. Lien for labor or materials furnished mill, factory or hoisting works
Foundrymen, boilermakers, and other persons who labor or furnish materials for the construction, alteration, repair or operation of a mill, factory or hoisting works at the request of the owner shall have a lien thereon for the amount due. If the hoist, factory or mill is located on property not belonging to the owner of the hoist, factory or mill, the purchaser at the sale on foreclosure of the lien may remove them within sixty days after the sale, whether the hoist, factory or mill is a fixture or not. If the hoist, factory or mill is located on a mine, mining claim or mill site which is the property of the owner, the lien shall embrace the surface ground, not exceeding five acres, upon which the hoist, factory or mill is located.