House Engrossed

 

public utilities; plant construction; colocation

 

 

 

 

State of Arizona

House of Representatives

Fifty-seventh Legislature

Second Regular Session

2026

 

 

 

HOUSE BILL 2457

 

 

 

 

AN ACT

 

amending title 40, chapter 2, article 6.2, arizona revised statutes, by adding section 40-360.14; relating to the power plant and transmission line siting committee.

 

 

(TEXT OF BILL BEGINS ON NEXT PAGE)

 


Be it enacted by the Legislature of the State of Arizona:

Section 1.1. Title 40, chapter 2, article 6.2, Arizona Revised Statutes, is amended by adding section 40-360.14, to read:

START_STATUTE40-360.14. Exemption; new plants colocated with extra high load factor customers

Notwithstanding sections 40-360.03 and 40-360.07, a utility, after providing thirty days' written notice to the commission and holding at least one public comment session in the county where the relevant plant is located, may construct a new plant without filing for or receiving a certificate of environmental compatibility for the new plant if all of the following conditions are met:

1. The new plant is colocated with an extra high load factor customer and the extra high load factor customer has received all applicable zoning entitlements.

2. The utility is a public service corporation or public power entity doing business in this state. END_STATUTE